Local Municipality Roadway Project
Prop 411 Package 7 – Tierra Del Sol
Scope of Work
This project includes the demolition of the existing sidewalk and roadway curb to construct new ADA-compliant side ramps. Spanning multiple miles of neighborhoods, Whelcon will also work on the surveying and adjustment of manholes, water valves, and monuments.
Key Project Elements
- 2,300 Square Feet of Concrete Sidewalk
- 8,664 Square Feet of Curb Access Ramps
- 281 Manhole Adjustments
- 311 Water Valve Adjustments
Project Location:
Tierra Del Sol, Tucson, Arizona
Project Owner:
City of Tucson
Project Timeline:
March 2024 – Expected Septmeber 2024
Contract Amount:
1,099,400.00