Scope of Work

Includes installation and maintenance of concrete wash out basin, removal of all concrete waste in the wash out basin. Installation of vertical concrete curb, concrete header, curb and gutter, median island curb and bike rack area curb.

Key Project Elements
  • Grouting of Base Plates at Canopy and Light Pole Bases
  • Vertical Curb and Gutter
  • Discharge Tank Foundation
  • Tank Ring Wall 24″X24″
  • Hydro Tank Footings

Project Location:

University of Arizona, Tucson

Project Owner:

Arizona Board of Regents

Project Timeline:

October 2021 – November 2022

Contract Amount:

$410,000.00