Local Municipality Utility, Rip Rap, and Concrete Project

Circle K at Ajo & Kinney

237990, NAICS CODES

Scope of Work

With the development of new infrastructure in West Tucson, Whelcon Contractors was employed to install an arch culvert on an overpass connecting a Circle K store to the surrounding neighborhoods. Whelcon also managed the placement of rip rap along the wash leading to the bridge as well as utilities.

Key Project Elements
  • Handrail Installation
  • 4 Cell Culvert with 12′-4″ x 4′-3″ Arch
  • 6″ Shotcrete Channel
  • Rip Rap with Fabric Lining 

Project Location:

Tucson, Arizona

Project Owner:

Circle K Stores, Inc.

Project Timeline:

April 2020 – June 2020

Contract Amount:

$ 287,300.00