Federal PCCP Project
Buckley Airforce Base Remove and Replace OWS
Scope of Work
Remove and Replace Oil Water Separator and Enclose Bay
Key Project Elements
- Excavation, shading and backfill of existing OWS system
- Demolition and disposal of AC, Concrete and existing OWS system
- Concrete flatwork, steel and fiber mesh reinforcement, trench drain and steel bollards
Project Location:
Buckley Air Force Base, Aurora, Colorado
Project Owner:
Four Tribes Construction Services, LLC
Project Timeline:
June 2019 – August 2019
Contract Amount:
$254,000.00
Before
After
Contact Us
Whelcon Contractors LLC
1 West Wetmore Road, Suite 203
Tucson, AZ 85705
Phone: (520) 314-2001